What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?

What could be a reason for a Product Owner to delay the start of a new Sprint after the conclusion of the previous Sprint?
A . The QA team has not finished testing the previous Increment before declaring it ready to ship.
B . The stakeholders were disappointed with the Increment produced in the previous Sprint.
C . There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint.
D . The Product Owner needs additional time to identify the next initiatives.
E . There’s not enough work in the Product Backlog to work on in the upcoming Sprint.

Answer: C