An agile team is working well together, but productivity has been flat.
What can the project leader do to help them improve performance?
A . Review the burndown chart to identify ways to increase efficiency.
B . Chair a weekly team retrospective focusing on identifying areas for continuous improvement.
C . Ask a senior manager to initiate a root-cause analysis.
D . Identify team key performance indicators (KPIs) and create positive incentives when targets are achieved.
Answer: A