Your customer has completed a successful Synergy Proof of Concept (PoC) consisting of a single frame with dual composers and dual Virtual Connect SE 40Gb F8 modules.
The customer wants to:
– add a second frame before they move into production
– have unified management
– have a separate logical enclosure for each frame
What are the basic steps to add the second frame? (Choose three.)
A . Move the standby composer to the second frame.
B . Disconnect the existing management ring, and then cable the FLM (frame link module) in the first frame to the FLMs in the second frame.
C . Install a satellite module in the first frame.
D . Move the bottom VC module from the first frame to the second.
E . Move one of the uplinks from the FLM in the first frame to a FLM in the second.
Answer: ABE