What are basic data that is needed to draw a Gnat Chart and Critical path network diagram?
I. Task
II. Duration
III. Code
IV. Dependencies
A . I, II, & III Only
B . I, II, & IV Only
C . I, II, III & IV
D . I, III, & IV Only
Answer: C
Explanation:
All of the basic data is needed to draw a Gantt Chart and Critical path network diagram