What are basic data that is needed to draw a Gnat Chart and Critical path network diagram?

Posted by: Pdfprep Category: CPIM-SMR Tags: , ,

What are basic data that is needed to draw a Gnat Chart and Critical path network diagram?

I. Task

II. Duration

III. Code

IV. Dependencies
A . I, II, & III Only
B . I, II, & IV Only
C . I, II, III & IV
D . I, III, & IV Only

Answer: C

Explanation:

All of the basic data is needed to draw a Gantt Chart and Critical path network diagram