A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.
What activity should the program manager perform next?
A . Program delivery management
B . Resource interdependency management
C . Program performance monitoring and controlling
D . Benefits sustainment and program transition
Answer: A