PdfPrep.com

What action needs to be taken?

A technician has completed a job and observed that more work is needed on the same asset. A new record is required to have the same asset, location and GL account.

What action needs to be taken?
A . Select Create Follow-up action from the completed work order
B . Select Create Work Order action from the completed work order
C . Select Create Work Package action from the completed work order
D . Click on the Plans tab, and add a new child work order from the completed work order

Answer: A

Explanation:

Reference: https://www.ibm.com/support/knowledgecenter/pt-br/SSANHD_7.6.0/com.ibm.mbs.doc/ wotrack/c_record_relationships_wos.html

Exit mobile version