Velocity is the:
A . total number of Product Backlog hours completed in an iteration divided by the number of developers.
B . measured rate at which teams turn Product Backlog items into running, tested features.
C . measured rate at which the project manager turns the Product Backlog into tested features.
D . total number of Product Backlog hours completed when developers work in pairs.
Answer: B