Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
A . Bottom-up
B . Parametric
C . Analogous
D . Three-point
Answer: C