Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Posted by: Pdfprep Category: CAPM Tags: , ,

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
A . 100
B . 120
C . 1,000
D . 1,200

Answer: A