Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Posted by: Pdfprep Category: CAPM Tags: , ,

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
A . Close Project or Phase
B . Conduct Procurements
C . Control Procurements
D . Close Procurements

Answer: D

Explanation: