PdfPrep.com

Under what circumstances should the Product Backlog be reprioritized?

Under what circumstances should the Product Backlog be reprioritized?
A .  The Scrum Master should reprioritize the Product Backlog only at the end of a new Sprint
B .  The Scrum Master should reprioritize the Product Backlog only at the beginning of a new Sprint
C .  The Team should reprioritize the Product Backlog only at the end of a new Sprint.
D .  The Product Owner should reprioritize the Product Backlog whenever new information is learned

Answer: D

Exit mobile version