Under what circumstances should the Product Backlog be reprioritized?
A . The Scrum Master should reprioritize the Product Backlog only at the end of a new Sprint
B . The Scrum Master should reprioritize the Product Backlog only at the beginning of a new Sprint
C . The Team should reprioritize the Product Backlog only at the end of a new Sprint.
D . The Product Owner should reprioritize the Product Backlog whenever new information is learned
Answer: D