Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?
A . Application design documentation
B . Business use cases
C . Test case documentation
D . Clauses in the contract
Answer: D