The CSIRT team is following the existing recovery plans on non-production systems in a PRE-BREACH scenario.
This action is being executed in which function?
A . Protect
B . Recover
C . Identify
D . Respond
Answer: A
The CSIRT team is following the existing recovery plans on non-production systems in a PRE-BREACH scenario.
This action is being executed in which function?
A . Protect
B . Recover
C . Identify
D . Respond
Answer: A