Posted by: Pdfprep
Post Date: November 15, 2020
The zero duration of milestones in project planning occurs because milestones:
A . Are unpredictable and challenge the Plan Schedule Management process.
B . Occur at random times in the project plans.
C . Represent a moment in time such as a significant project point or event.
D . Represent both significant and insignificant points in the project and are difficult to anticipate.
Answer: C
Leave a Reply