The variable overhead expenditure variance is:
A . The over or under absorbed variable overhead
B . The difference between the actual hours worked and the standard hours produced, multiplied by the variable overhead absorption rate
C . The actual hours worked multiplied by the variable absorption rate
D . The difference between the variable overheads incurred and the flexed budget allowance for variable overheads
Answer: D