The team is creating plans at the Strategy Horizon. Diverse opinions are delaying this effort because different people are focused on different timeframes. After some discussion the team realizes they need to focus their efforts on the following viewpoint:
A . Business view of the teams working on the initiatives
B . Micro-view of the potential changes to the organization
C . Broader view of the impact of the change to the organization
D . Local view of the effect on the community.
Answer: C