The scope management plan and scope baseline are contained in:
A . organizational process assets
B . a requirements traceability matrix
C . the project charter
D . the project management plan
Answer: D
The scope management plan and scope baseline are contained in:
A . organizational process assets
B . a requirements traceability matrix
C . the project charter
D . the project management plan
Answer: D