The purpose of "setting the stage” in a project retrospective is to:
A . Restate the goal of the meeting and create an open atmosphere.
B . Review the scope statement and summarize project results.
C . Elevate the team’s morale and ensure that everyone participates.
D . Describe the next Iteration and discuss lessons learned.
Answer: A