The Project Board needs to assess project viability at certain points as defined in the Project Plan. How does the Progress theme assist this?
A . Sending regular Checkpoint Reports
B . Authorizing one stage at a time
C . Creating Exception Reports when tolerances are threatened
D . Reports during project closure
Answer: B