Posted by: Pdfprep
Post Date: December 24, 2020
The process of identifying and documenting relationships among the project activities is known as:
A . Control Schedule.
B . Sequence Activities.
C . Define Activities.
D . Develop Schedule.
Answer: B
Explanation:
Process: 6.3 Sequence Activities
Definition: The process of identifying and documenting relationships among the project activities.
Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
Inputs
Leave a Reply