The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Posted by: Pdfprep Category: CAPM Tags: , ,

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
A . Plan Schedule Management.
B . Develop Project Charter.
C . Develop Schedule.
D . Plan Scope Management.

Answer: A

Explanation:

Process: 6.1 Plan Schedule Management

Definition: The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.