The primary purpose of the stakeholder register is to:

Posted by: Pdfprep Category: CAPM Tags: , ,

The primary purpose of the stakeholder register is to:
A . Record stakeholder issues on the project
B . Maintain lessons learned earlier in the project
C . Maintain a list of all project stakeholders
D . Document change requests and their status

Answer: C

Explanation: