PdfPrep.com

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
A .  adaptive
B .  reflexive
C .  predictive
D .  iterative

Answer: A