The most appropriate model for a geographically distributed project team is one in which the team is distributed across:

The most appropriate model for a geographically distributed project team is one in which the team is distributed across:
A . relatively few locations, with each location team comprised of a complete development group developing decoupled subsystems.
B . locations in the same time zone, working on the same systems while leveraging rich communication channels.
C . relatively few locations, and tasks are divided along functional lines with design in one location, coding in another, and testing in another.
D . many locations, with relatively few people at each location developing and testing decoupled subsystems.

Answer: A