The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
A . Scope, People & Resources, Benefit
B . Scope, Risk, Product
C . Risk, Benefit, Product
D . Scope, Risk, Benefit
Answer: D