The following chart represents metrics related of a project that was completed. Indicate what is represented by the lines A, B, and the axes X, Y
A . X C Time
Y C Percent
A – % of functional tests in the test suite
B – % of non-functional tests in the test suite
B . X C Time
Y C Cost
A C Cost of test (per week)
B C Cost of finding a single bug (per week)
C . X C Time
Y C Number of defects
A C Number of open defects
B C Number of closed defects
D . X C Time
Y C Count
A C Total number of executed tests
B C Number of open bugs
Answer: D