PdfPrep.com

The difference between the latest event time and the earliest event time in a project network analysis is referred to as:

The difference between the latest event time and the earliest event time in a project network analysis is referred to as:
A . Critical Activity
B . Float
C . Critical Path
D . Node

Answer: B

Exit mobile version