The delivery team is in a meeting identifying cycle time improvement opportunities for delivery of the final product. They decide to apply the following technique:
A . Backlog management
B . Value stream mapping
C . Story decomposition
D . Story mapping
Answer: B
Explanation:
Value stream mapping complete, fact-based, time-series representation of the stream of activities required to deliver a product or service.