Posted by: Pdfprep
Post Date: March 5, 2021
The critical path for any project is the path that exhibits which of the following characteristics?
A . Has the longest duration in time.
B . Costs the most money.
C . Requires the largest amount of labor
D . Is deemed most important to the project.
Answer: A
Leave a Reply