The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
A .  Project management plan.
B .  Project charter.
C .  Work breakdown structure.
D .  Stakeholder register.

Answer: B