The business needs, assumptions, and constraints and the understanding of the customers’ needs and high-level requirements are documented in the:

The business needs, assumptions, and constraints and the understanding of the customers’ needs and high-level requirements are documented in the:
A . Project management plan.
B . Project charter.
C . Work breakdown structure.
D . Stakeholder register.

Answer: B