Internal dependencies are likely to be linked to the scope of a corporate portfolio
Internal dependencies are likely to be linked to the scope of a corporate portfolioA . Only 1 is trueB . Only 2 is trueC . Both land 2are trueD . Neither 1 or 2...
Internal dependencies are likely to be linked to the scope of a corporate portfolioA . Only 1 is trueB . Only 2 is trueC . Both land 2are trueD . Neither 1 or 2...
What role description includes support for project assurance and health checks which is independent of the projects?A . Programme ManagerB . Business Change ManagerC . Senior Responsible OwnerD . Programme OfficeView AnswerAnswer: D
Which information is NOT generally found in the Business Case?A . Value of the benefitsB . Costs of delivering the BlueprintC . Strategic risks to the programmeD . Definition of internal controlsView AnswerAnswer: D
Which is a part of programme planning?A . Ensuring the programme manages its projects in detailB . Involving widespread discussions to include ambiguities and unknownsC . Checking the sustainability of the programme against the...
Which document is updated throughout the programme when new information on benefits and risks becomes available?A . Benefits Management StrategyB . Business CaseC . Programme BriefD . Information Management PlanView AnswerAnswer: B
Which BEST defines something that could have an unfavourable effect on programme objectives?A . RiskB . OpportunityC . ThreatD . Dis-benefitView AnswerAnswer: C
What does the ‘I’ stand for in POTI, the model that helps with Blueprint development?A . InvestmentB . ImplementationC . InductionD . InformationView AnswerAnswer: D
Which would you NOT expect to find in a Programme Brief?A . Outline vision of the future stateB . Current issues and potential risksC . Clarification of what the programme can achieveD . Roles...
What document provides terms of reference for the Sponsoring Group?A . Programme BriefB . Quality and Assurance StrategyC . Resource Management PlanD . Organization StructureView AnswerAnswer: D
What does the 'O' stand for in POTI, the model that helps with Blueprint development?A . OutcomeB . Organizational structureC . OutputsD . Operational modelsView AnswerAnswer: B