Which information is included in Benefit Profiles?
Which information is included in Benefit Profiles?A . Scheduled reviewsB . Dependent capabilitiesC . Procedures to avoid double countingD . Information audit requirementsView AnswerAnswer: B
Which information is included in Benefit Profiles?A . Scheduled reviewsB . Dependent capabilitiesC . Procedures to avoid double countingD . Information audit requirementsView AnswerAnswer: B
What role, in approving the design of the programme, has a focus on compliance with corporate controls?A . Programme OfficeB . Programme ManagerC . Senior Responsible OwnerD . Business Change ManagerView AnswerAnswer: C
What is the step in the Benefits Management Cycle that includes carrying out activities to transition the capabilities delivered by the projects into outcomes?A . Deliver benefits realizationB . Identify benefitsC . Develop the...
Which information is included in Benefit Profiles?A . Scheduled reviewsB . Dependent capabilitiesC . Procedures to avoid double countingD . Information audit requirementsView AnswerAnswer: B
Which is a trigger for a compliance programme?A . The corporate board has created a vision for changeB . A number of stand-alone projects would benefit from better coordinationC . The organization has to...
Which label refers to one of the organizational risk perspectives?A . OperationalB . PoliticalC . PortfolioD . EconomicView AnswerAnswer: A
Which is represented in a summary risk profile?A . Category of risk responseB . Impact of an issueC . Likelihood of a riskD . Cause of a riskView AnswerAnswer: C
Which statement refers to programme plans?A . Describe the resourcing of programme activitiesB . Present the rules for all parts of the organizationC . Describe why and how something will be undertaken in a...
Include the costs for tools to track and report on progress,A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 is...
What document describes how the roles in the programme team relate to each other?A . Stakeholder ProfilesB . BlueprintC . Project DossierD . Organization StructureView AnswerAnswer: D