Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
A . Continuous
B . Discrete
C . Regulated
D . Arbitrary
Answer: A
Explanation:
Process: 13.1 Identify Stakeholders
Definition: The process of identifying the people, groups,
or organizations that could impact or be impacted by a decision, activity, or
outcome of the project; and analyzing and documenting relevant information
regarding their interests, involvement, interdependencies, influence, and
potential impact on project success.
Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.
Inputs