Stakeholder identification and engagement should begin during what phrase of the project?
A . After the project management is completed
B . After the stakeholder engagement plan is completed
C . As soon as the project charter has been approved
D . After the communications management plan is completed
Answer: C
Explanation:
Reference: https://pmstudycircle.com/2012/06/identify-stakeholders-project-management/