Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?

You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information: Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14 pontos Sprint 5: 15 pontos

Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
A .  6
B .  5
C .  4
D .  3

Answer: B