Reviewing historical risk events is MOST useful for which of the following processes within the risk management life cycle?
A . Risk mitigation
B . Risk assessment
C . Risk monitoring
D . Risk aggregation
Answer: B
Reviewing historical risk events is MOST useful for which of the following processes within the risk management life cycle?
A . Risk mitigation
B . Risk assessment
C . Risk monitoring
D . Risk aggregation
Answer: B