Project managers use velocity to determine:
A . If the team is committing to an appropriate amount of work for the iteration.
B . How much work each team member is capable of completing during an iteration.
C . How much work teams that are similar in size are capable of completing during an iteration.
D . If the Product Owner is prioritizing work appropriately in preparation for iteration planning.
Answer: A