Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
A .  Verified deliverables.
B .  Validated deliverables.
C .  Acceptance criteria.
D .  Activity resource requirements.

Answer: A