Once the make-or-buy analysis is completed, which document defines the project delivery method?

Posted by: Pdfprep Category: CAPM Tags: , ,

Once the make-or-buy analysis is completed, which document defines the project delivery method?
A . Procurement statement of work (SOW)
B . Procurement strategy
C . Terms of reference
D . Change request

Answer: B

Explanation:

Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-13-procurement-management­project-management/