Posted by: Pdfprep
Post Date: December 12, 2020
On a team new to Scrum, two team members are disrupting the daily standup with a side conversation. The ScrumMaster should:
A . wait until the standup is over and then talk to the disruptive team members.
B . immediately intervene to remedy the disruptive situation.
C . record the issue and then raise the issue at the Sprint Retrospective.
D . wait for the empowered, self-organizing team to resolve the issue.
Answer: B