Listed below are some responsibilities of a Scrum Master. Identify the one that is NOT correct.
A . Coordinates with Product Owner in creation of the Prioritized Product Backlog.
B . Facilitates Prioritized Product Backlog Review Meetings.
C . Resolves the issues affecting the Scrum Team.
D . Identifies risks and implements risk mitigation actions.
Answer: A
Explanation:
Reference: http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf