J has been appointed project manager for a multimillion dollar upgrade to factory computer systems for his international organisation.
The organisation has decided to adopt the PRINCE2 project management methodology, of which J has knowledge from a previous post, but this was some time ago and his knowledge may need updating.
In order to achieve maximum success, J realises he will need to ensure that problems encountered at each phase of the project are used to inform later stages of the project.
Advise J at which stage of the project lessons learned should be recognised and applied to later stages, in order to prevent recurrence during the project:
A . Starting the project
B . Initiation of the project
C . Managing stage boundaries
D . Controlling a stage
Answer: C