The project is in stage 2. The project manager is reviewing stage status and has collected the checkpoint reports from the team managers. These show that the products are being completed on schedule. However, project support has raised issues that quality reviews have not been completed as agreed. The project manager reports in the highlight report that the stage is progressing well.
Is this appropriate, and why?
A . Yes, because the highlight report is a summary of the information in the checkpoint reports.
B . Yes, because the highlight report is used to provide the project board with stage and project progress.
C . No, because the project manager should have recorded the cause of the delay to the quality reviews in the lessons log.
D . No, because the issues raised by project support are a cause for concern and should be reflected in the highlight report.
Answer: D
Leave a Reply