In which process may a premature close of the project be authorized?
A . Directing a Project
B . Controlling a Stage
C . Managing a Stage Boundary
D . Closing a Project
Answer: A
In which process may a premature close of the project be authorized?
A . Directing a Project
B . Controlling a Stage
C . Managing a Stage Boundary
D . Closing a Project
Answer: A