In which process is it decided that an Exception Plan should be created to replace a Stage Plan?

In which process is it decided that an Exception Plan should be created to replace a Stage Plan?
A . Directing a Project
B . Controlling a Stage
C . Managing a Stage Boundary
D . Closing a Project

Answer: A