Posted by: Pdfprep Category: C_ACTIVATE05 Tags: SAP Certified Associate, C_ACTIVATE05 exam questions, C_ACTIVATE05 practice exam Post Date: February 22, 2021 Pdfprep2021-02-22T16:13:47+00:00 In which phase of the SAP Activate methodology does the team complete the Transformation Planning? Please choose the correct answer.A . DeployB . ExploreC . PrepareD . Realize View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.