In which of the Risk Management processes is the project charter used as an input?

In which of the Risk Management processes is the project charter used as an input?
A . Plan Risk Responses
B . Implement Risk Responses
C . Plan Risk Management
D . Perform Quantitative Risk Responses

Answer: C

Explanation:

Reference: https://www.projectengineer.net/project-risk-management-according-to-the-pmbok/