In which of the following stages will you be most actively involved?

Posted by: Pdfprep Category: SMC Tags: , ,

Suppose you are a Scrum Master or a Scrum Team that is progressing through Tuckman’s model of Group Dynamics.

In which of the following stages will you be most actively involved?
A . Forming
B . Storming
C . Norming
D . Performing

Answer: A

Explanation:

Reference: https://project-management.com/the-five-stages-of-project-team-development/

Leave a Reply

Your email address will not be published.